Here’s what actually happens.
Once an application is submitted, there’s usually a week or two before it’s validated. Validation just means the council has checked the paperwork is complete. If anything is missing, which happens more often than you’d think, the clock doesn’t start until it’s fixed.
After validation comes the consultation period. Neighbours get notified, a site notice goes up, and statutory consultees like the highways department have their say. This takes a minimum of 21 days but can stretch longer if objections come in or the case officer needs extra reports.
Then the case officer writes their recommendation. For straightforward householder applications, this goes through delegated powers and a decision is issued. For anything contentious or larger in scale, it goes to the planning committee, which adds another three to six weeks depending on when the next meeting is.
In practice, most straightforward extensions and loft conversions get a decision in 8 to 12 weeks. Anything involving a conservation area, a listed building, or a new dwelling can easily take 16 weeks or more.
The bit most tradespeople don’t realise is that the decision notice isn’t the end. There’s usually a conditions discharge stage before work can actually start, and that can add several more weeks if the council is slow to respond.
If you’re a builder trying to line up work, the useful bit of information is the decision date, not the submission date. That’s the point where the homeowner actually has the go-ahead and starts looking for quotes.